The Living Shorelines initiative is an innovative and ongoing program of works that will use a combination of nature-based solutions and engineered methods to minimise long-term coastal erosion at a number of locations across the city.
The initiative is part of Council’s broader Coastal Hazard Adaptation Strategy (CHAS) and is being delivered under the QCoast2100 program that is funded by the Queensland Government and delivered by the Local Government Association Queensland.
The pilot project at Three Paddocks Park in Birkdale will trial a number of the methods that are planned to be used in the ongoing Living Shorelines initiative. Construction on this small project commenced in June 2025 and took approximately eight weeks to complete.
Council is committed to ensuring the safety of its officers and the public throughout the lifecycle of the project and the works undertaken complied with all relevant legislative safety and environmental requirements. Restoring our natural environment and protecting our native fauna and flora is one of Council’s top priorities. No works were carried out in the nearby creek in recognition of the bale of sea turtles that call it ‘home’.
There were no plans to build a permanent, concrete slab in Three Paddocks Park. A temporary gravel track provided safe access for a crane during construction and did not impact the area’s natural stormwater flows.
Temporary fencing has been installed to allow the newly planted vegetation to become established and protect the seed trapping devices. We are monitoring the site regularly and the fencing will be removed once the vegetation has reached an appropriate level of maturity. We're unable to provide a timeframe at this stage, however it is likely to take a number of months.
The second pilot project at Oyster Point Park in Cleveland is trialling several methods we expect will be used in the ongoing Living Shorelines initiative. Construction on this small project carried out and completed in August 2025.
Importantly, there was no excavation of the surface, as part of a no-dig design/construction, to ensure cultural heritage values of foreshores were not disturbed by works.
Restoring our natural environment and protecting our native fauna and flora is one of Council’s top priorities. The works were undertaken outside of times when shorebirds are expected to be at site and therefore were not impacted.
Importantly, Council designed the works to not involve any surface excavation and piloted an innovative no-dig design that ensured the works carried out did not disturb or cause harm to Aboriginal cultural heritage.