We are currently upgrading a number of roads, car parks, parks, footpaths, marine works, cycle ways, and intersections across the Redlands that have been identified as improvements under our current budget.

Contact us if you need more information or have feedback about problems in your area.

Listed below are current and upcoming works for each suburb grouped by 

  • City Operations - City Sport & Venues, Parks & Conservation, Roads Drainage & Marine.
  • City Infrastructure - Civic & Open Space
  • Project based works - Construction Projects

 

City Operations

- Paperbark Removal and Replacement Program - Various Locations across Redland City Council areas
RCC contractor will complete Paperbark removal and replacements. Affected residents and neighbors will receive a notification one week prior. Work (removal, stump grinding, and replanting if needed) will take 48 hours per location. Locations attached. - No Road Closure raffic Control and/or advisory signs will be placed in locations where traffic may be impacted.. This work is planned to commence Thursday 1 May 2025 and to be completed by Thursday 31 July 2025 between the hours of 7:00 AM and 3.30 PM (weather permitting).
Redland Bay - Refresh Line Marking from 37 Boundary St to 42 Meissner St Redland Bay - 37 Boundary St to 42 Meissner St Redland Bay
Refresh Line Marking from 37 Boundary St to 42 Meissner St Redland Bay. Works will be completed as Night Works. Traffic control will be on site to assist pedestrians and motorists. - No Road Closure. This work is planned to commence Monday 14 July 2025 and to be completed by Monday 21 July 2025 between the hours of 7.00pm and 2.30am (weather permitting).
- Asphalt Maintenance Works (Night Works) - 381-387 Main Road and 7 Waterloo Street Wellington Point
Asphalt Maintenance Works. Partial lane closures will be implemented and local access for vehicles and pedestrians will be provided. - No Road Closure. This work is planned to commence Thursday 31 July 2025 and to be completed by Friday 1 August 2025 between the hours of 07.00pm and 02.30am (weather permitting).

City Infrastructure

Victoria Point - Sewer Main Extension/Connection - Carnoustie Court,
City Water Contractors are undertaking sewer works to connect a new subdivision, with works expected to take 4 weeks to complete, weather permitting. - Full Road Closure Daytime road closure with traffic control in place. These works are planned to occur between the hours of 6.30 am and 5.00 pm, commencing on Tuesday 4 June 2024 and completed by Friday 28 June 2024, weather permitting.

Projects

Alexandra Hills - PDG-64008-1 - Switchboard Pump Stations – SPS 008 McDonald Road, Alexandra Hills
Description of Works: Redland City Council Contractors will be completing the construction and installation of the SPS008 switchboard and associated works. Timeline: 19 May 2025 through to 31 July 2025, 7.00am to 5.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Birkdale - PDG-55092-5 - Judy Holt Park Northern Remediation Project
Judy Holt Park Birkdale is a closed landfill site. To maintain adherence to stringent environmental laws, critical remediation works are to be carried out to protect the surrounding environment. This will include recapping old landfill beneath the park’s rugby union fields to prevent leachate breakouts, potentially affecting the environment. The works will also deliver improved playing surfaces, an extra playing field and provide better, higher-capacity sports facilities and a much-improved public open space. Expected Start Date - 17/02/2025 Expected Finish Date - 26/09/2026 (weather & site conditions permitting).
Birkdale - PDG-44887-1 - Footpath Renewal to Aquatic Paradise Park West, Birkdale
Redland City Council Contractors will be undertaking the installation of new sections of concrete footpath, removal of sections of existing asphalt footpath, turf to disturbed areas and associated works. Expected Start Date - 14/07/2025 Expected Finish Date - 28/08/2025 (weather & site conditions permitting)
Cap - PDG-43694-1 - Pathway Lighting – Holland Crescent to Shopping Centre
Redland City Council Contractors will be undertaking the installation of footpath lighting, including 5 poles, new pits, a main switchboard, turf to disturbed areas and associated works. Expected Start Date - 31/03/2025 Expected Finish Date - 15/08/2025 (weather & site conditions permitting)
Cleveland - PDG-20276-4 - Redlands Performing Arts Centre (RPAC) Forecourt Construction
Redland City Council Contractors will - • Demolish and remove the existing forecourt roofs; • Retain and protect the existing feature trees on the RPAC footpath; • Construct: o New Stairs, ramps and access points, o Reconfiguration of the pedestrian access to the main buildings including associated civil and landscaping works; o Awning and trellis construction; o Alfresco deck and seating; o Lighting upgrading; o Stormwater drainage treatment; o Electrical upgrade; and o Signage. Expected Start Date: 02/12/2024 Expected Finish Date: 02/08/2025 (Weather and site conditions permitting)
Cleveland - PDG-63038-2 - Switchboard Renewal Upgrades - SPS141 South Street, Cleveland
Description of Works: Redland City Council Contractors will be designing, constructing and installing a new switchboard, new disconnect box, new odour control unit including new vent pole, new concrete slabs, wider driveway, new fencing, bollards & gates, new stormwater pits (site drainage), and new antenna pole. Timeline: 10th February through to 25th July 2025, 7.00am to 6.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions. Should the date move further than 1 week from the above proposal an updated Notification will be issued.
Cleveland - PDG-44219-1 - Electrical Upgrade – Raby Bay Foreshore Park, Cleveland
Redland City Council contractors will be installing a weatherproof electrical power supply box with GPO outlets for use by commercial operators and associated works. Expected Start Date - 16/06/2025 Expected Finish Date - 30/07/2025 (weather & site conditions permitting)
Cleveland - PDG-20820-1 - Gate Restoration - Norm Price Park, Redlands Showground, Cleveland
Redland City Council Contractors will be restoring the Norm Price Park entrance gate with a new panel, planting, turf to disturbed areas and associated works. Expected Start Date - 10/07/2025 Expected Finish Date - 23/07/2025 (weather & site conditions permitting)
Cleveland - PDG-60008-2 - Living Shoreline - Oyster Point, Cleveland
Benefits: The benefits of this project will help reduce the ongoing impact of coastal erosion along the foreshore and maintaining the long-term integrity of the coastline and revegetation and mangrove trapping will support natural habitat regeneration. Description of Works: Construction Projects Unit will be undertaking works that will use a combination of nature-based solutions and engineered methods to minimise long-term coastal erosion to the foreshore of Oyster Point, Cleveland. These works will include: • Placement of concrete block mattress to the boat ramp and drop down Bollard • Installation of Mass blocks to assist with the erosion of the foreshore • Revegetation of the area with coastal plants; and • Any other associated works required to complete the project. Small watercraft access from the ramp may be restricted at times. Timeline: Wednesday 13th August 2025 through to Friday 29th August 2025, 7.00am to 6.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Macleay Island - PDG-44096 - Footpath Install - Brighton Road, Macleay Island
Redland City Council's Internal Construction crews with assistance from contractors will be completing footpath upgrade works on Brighton Road, Macleay Island. Works will involve, but not limited to: • Construction of pathway and pram ramps. • Installation of kerb & channel. • Installation of a headwall & gully unit. • Installation of a block retaining wall. • Landscaping works. • Any other associated works to complete this project. Timeline: Tuesday 27th May 2025 through to Tuesday 30th September 2025, 7.00am to 5.00pm, Monday to Friday. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Point Lookout - PDG-46704-1 - Shelter Renewal – Cylinder Beach Foreshore
Redland City Council Contractors will be undertaking the installation of a new shade shelter with custom laser cut coastal graphics, concrete slab, table setting, electric BBQ, the installation of turf to disturbed areas and associated works. These works also include the removal of existing poor conditioned slabs, table setting, BBQ. Expected Start Date - 23/07/2025 Expected Finish Date - 08/08/2025 (weather & site conditions permitting)
Point Lookout - PDG-44219-2 - Electrical Upgrade – Cylinder Beach Foreshore
Redland City Council contractors will be installing a weatherproof electrical power supply box/outlet distribution board with GPO outlets and smart meters for use by commercial operators, turf to disturbed areas and associated works. Expected Start Date - 14/07/2025 Expected Finish Date - 05/08/2025 (weather & site conditons permitting)
Redland Bay - PDG-64201-1 - SPS112 Rising Main Renewal – Redland Bay
Redland City Council Contractors will be constructing a new 795m long sewer rising main for Sewer Pump Station 112 which will replace the existing rising main, completing upgrades at Sewer Pump Station 112 and other associated works. Exepcted Start Date - 10/02/2025 Expected Finish Date - 18/07/2025 (weather & site conditions permitting)
Redland Bay - PDG-44692 - The Esplanade, Redland Bay – Foreshore Stabilisation
Redland City Council’s internal construction crews with assistance from contractors, will be undertaking emergency repairs on the revetment wall along the Esplanade, Redland Bay. The project will involve delivering and installing approximately 1,000 tonnes of rock over a 120-meter section of the foreshore, along with associated works. Timeline: Monday 9th June through to Friday 12th September 2025, 7.00am to 5.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Redland Bay - PDG-64111-1 - Switchboard Pump Stations – SPS 111 Christopher Street, Redland Bay
Description of Works: Redland City Council Contractors will be completing the construction and installation of the SPS111 switchboard and associated works. Timeline: 26 May 2025 through to 08 August 2025, 7.00am to 5.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Redland Bay - PDG-64138-1 - Switchboard Pump Stations – SPS 138 Penzance Drive
Description of Works: Redland City Council Contractors will be completing the construction and installation of the SPS138 switchboard and associated works. Timeline: 11 June 2025 through to 29 August 2025, 7.00am to 5.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Russell Island - PDG-30908 - Drainage Upgrade - Highland Ridge Road, Russell Island
Redland City Council's Internal Construction crews with assistance from contractors will be completing stormwater drainage upgrade works on Highland Ridge Road & Barcelona Terrace, Russell Island QLD 4184. Works will involve, but not limited to: • Construction of a new open drain. • Installation of road crossings. • Installation of stormwater pipes and a grated field inlet pit. • Extension of an existing open drain. • Any other associated works to complete this project. Timeline: Tuesday 5th August through to Friday 22nd August 2025, 7:00am to 5:00pm, Monday to Friday. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Thornlands - PDG-64515-3 - Kinross Road Sewer Trunk Gravity Sewer Main
Description of Works: Redland City Council Contractors will be designing and constructing a new sewer main including all live connections between the existing and new sewer. Decommissioning SPS147 and diverting sewage flows into the new gravity sewer main. Timeline: 2 May 2025 through to 17 December 2025, 7.00am to 6.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions. Should the date move further than 1 week from the above proposal an updated Notification will be issued.
Victoria Point - PDG-64055-1, 64056-1, 64060-1 - Switchboard Pump Stations - SPS 055, SPS 056, SPS 060
Description of Works: Redland City Council Contractors will be completing the construction and installation of the SPS 055, SPS 056 & SPS 060 switchboards and associated works. Timeline: 26 May 2025 through to 08 August 2025, 7.00am to 5.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions. Location: SPS 055 - Behind 16 Wilson Lane, Victoria Point (Southern end of Wilson Street) SPS 056 - 10 Wilson Street, Victoria Point (Northern End) SPS 060 – 3 Orana Street, Victoria Point (Corner Orana Esplanade)
Victoria Point - PDG-64135-1 - Switchboard Pump Stations – SPS 135 Aspect Drive, Victoria Point
Description of Works: Redland City Council Contractors will be completing the construction and installation of the SPS135 switchboard and associated works. Timeline: 02 June 2025 through to 15 August 2025, 7.00am to 5.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Victoria Point - PDG-64022-1 - Switchboard Pump Stations – SPS 022 Link Road, Victoria Point
Description of Works: Redland City Council Contractors will be completing the construction and installation of the SPS022 switchboard and associated works. Timeline: 21 May 2025 through to 01 August 2025, 7.00am to 5.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.
Wellington Point - PDG-60008-1 - Living Shoreline - Three Paddocks Park
Benefits: The benefits of this project will help reduce the ongoing impact of coastal erosion along the foreshore and maintaining the long-term integrity of the coastline and revegetation and mangrove trapping will support natural habitat regeneration. Description of Works: Construction Projects Unit will be undertaking works that will use a combination of nature-based solutions and engineered methods to minimise long-term coastal erosion to the foreshore of 318-324 Birkdale Road, Wellington Point. These works will include: • Revegetation of the area • Placement of logs to mitigate further foreshore erosion • Installation of Mangrove trapping devices • Installation of Fencing • Installation of Coir logs • Any other associated works to complete this project. No works are planned within the creek and pedestrian access and pathways may be restricted at times. Timeline: Monday 30th June 2025 through to Friday 15th August 2025, 7.00am to 5.00pm. This completion date may change over the course of the project due to wet weather and resultant poor site conditions.